Subdivision Inspection Fee
Fees are due prior to issuance of a zoning clearance or approved construction plans. Re-inspection fees shall be paid prior to final construction approval of the subdivision.
- Minor subdivisions (25 lots or fewer) $400 + $3 per lot
- Subdivisions with more than 25 lots $600 + $6 per lot
- For subdivisions that are phased, the initial fee of $400 or $600, whichever applies, shall be paid with the first phase plus the per lot fee associated with the first phase. The per lot fee for subsequent phases shall be due upon initiation of construction of each phase.
- First final inspection - no charge
- First re-inspection - no charge
- Subsequent re-inspections - $250 per inspection
Site Inspection Fee
Fees are due upon receipt of a zoning clearance or approved construction plans. Re-inspection fees shall be paid prior to final construction approval of the project by the City.
- Sites 10,000 square feet impervious area or less: $250
- Sites greater than 10,000 square feet impervious area: $25 per 1,000 square feet
- Out-parcels on previously inspected site: $250
- First final inspection - no charge
- First re-inspection - no charge
- Subsequent re-inspections - $250 per inspection
Individual Inspections
Re-inspection fees shall be paid prior to issuance of certificate of occupancy
- First Inspection - no charge
- Re-inspections - $50 per inspection
Inspection Fee other than Normal Working Hours
- Rate per hour, minimum half hour increments - $40
- Four hour minimum per request - $160
The inspections listed are per Resolution Number 1178
For questions, please contact 352-241-7335